Project Overview
Location : 150 kilometers north from
Baku(Capital)
Area : 72,000,000m2
Planned Pop. : 500,000 people
(1st stage 100,000)
Project Cost : USD 28.7 billion
Project Period : 2009~2011(3 years)
PM Fee : 23,94 0,000 euro
PM scope : General Plan & 1st stage Executive Design
Project Details
07.04 President of Azerbaijan visited Korea Land Corporation
07.10 Signing of MOU (Ministry of Land, Transportation, and
Maritime Affairs ? Azerbaijans Ministry
of Ecology and Natural Resources)
07.12 Working-level committee held
08.01 PM contract (proposal) submitted,negotiations held
08.11 Completion of negotiations in detail including PM fee
08.12 Signing of PM contract in Azerbaijan(Ministry of Land,
Transportation, and Maritime Affairs ?Ministry of
Ecology and Natural Resources)
Source: http://globalproject.lh.or.kr/